Project Updates

FUTURE_next.exit_.roadsign_jpeg

Transportation Project Summaries

Street Projects

Heart of Bryant Reynolds Road Improvements

Status:

  • Project Press Release
  • Construction Contract for JCI is ready to be executed following ARDOT Concurrence of Award

Schedule:

  • Final Plans Submitted:              August 2017
  • Expected ARDOT Approval:     September 2017
  • Planned Construction Date:      April 2018
  • Low Bid was JCI Construction
  • Anticipated Completion             November 2018

Bryant Parkway: Interstate 30 to Shobe Road (Project 1)

Status:

  • Earthwork is to grade from Raymar Rd to Hunter Lee. Beginning grading from Hunter Lee to Shobe Road. 

Schedule:

  • Construction Start Date          In Progress
  • Anticipated Completion          May 2019

Bryant Parkway Shobe Road to Reynolds Road (Project 2)

Status:

  • Alternative B is currently being pursued as the preferred alternative after other route were disqualified. 
  • 30% Roadway and Bridge plans for Bryant Parkway from Shobe to south side of bridge are complete and will be submitted to the city in September.
  • Coordinating with Entergy to raise Transmission Lines where required.

Schedule:

  • Topo Surveys                      Completed
  • Parcel Surveys                    Completed
  • 30% Submittal                     In progress
  • 60% Submittal                     December 2018
  • 90% Submittal                     January 2019
  • Final Submittal                     March 2019
  • Planned Construction Start  April 2019

(N) Bryant Parkway: Highway 5 to Hilldale Road

Status:

  • Township is continuing to work on Shared Use Path and Driveways.

Schedule:

  • Construction                              In Progress
  • Anticipated Completion             October 2018

Bryant Pkwy/Hilldale Rd Intersection Improvements

Status 

  • Top Surveys Completed
  • Design contract submitted to city for review

Schedule

  • 30% Submittal                       December 2018
  • 60% Submittal                       February 2019
  • Final Submittal                       March 2019
  • Anticipated Completion         April 2019


Sidewalks

Sidewalks at Elm Street and Third Street

Status:

  • 60% Construction Plans have been submitted to the city for review. 

Schedule:

  • Design Surveys                          Completed
  • 10% Submittal                            Completed
  • 60% Submittal                            Completed  
  • Final Submittal                           October 2018
  • Construction Begins                   October 2018    

imagejpeg_0

Fire Station Project Summaries

Springhill Fire Station 

Status:

  • Land Purchase Complete         September 2017
  • Goes out to Bid                         October 2017
  • Construction 85% Complete     August 2018


Schedule:

  •  Bid Review Day                        November 9, 2017  
  • City Council Approval                November 2017
  • Construction Begins                  January 2018
  • Construction Complete              November 2018

Hill Farm Fire Station 

Status:

  • Land Purchase Complete         September 2017
  • Goes out to Bid                         October 2017
  • Construction 85% Complete     August 2018

Schedule:

  • Bid Review Day                         November 7, 2017
  • City Council Approval                November 2017
  • Construction Begins                  January 2018
  • Construction Complete              November 2018

           

Parks and Recreation Projects Summaries

*Project designs and timelines are subject to change as projects progress.

Mills Park Restroom Facility

Status:

  • Completed

Shade Structures Bishop Park

Status:

  • Completed

New Grounds Building Bishop Park

Status:

  • Currently Under Construction

Schedule:

  • Anticipated Completion Date        October 2018

New Park- North of Interstate

Status:

  • Land Purchase Completed- Approximately 40 acres west of Midland Park
  • Future plans include additional soccer fields along with walking and biking trails

Schedule:

  • To Be Announced


Bishop Center Remodel

Status:

  • Currently Under Construction

Schedule:

  • Anticipated Completion Date            October 2018

Bishop Parking Lot and Landscaping

Status:

  • Goes out to Bid                         June 2018

Schedule:

  • City Council Approval                 June 2018
  • Work Begins                               August 2018
  • Anticipated Completion              October 2018  

Mills Parks All Inclusive Playground

Status:

  • Phase 1 Completed

Mills Park Trails Update 

  • Info coming soon!      

Stormwater Project Link

Stormwater ProjectsWebsite Photo Water

 

Bryant School District

Bryant School Logo

Bryant School District Facilities Moving Forward



Sign up today for Notify MeNotify MeStay up to date on ALL City News and Events