Project Updates

FUTURE_next.exit_.roadsign_jpeg

Transportation Project Summaries

Street Projects

Heart of Bryant Reynolds Road Improvements

Status:

  • Awaiting final approval from ARDOT to advertise for bids

Schedule:

  • Final Plans Submitted:               August 2017
  • Expected ARDOT Approval:      September 2017
  • Planned Construction Date:       October 2017

Bryant Parkway: Interstate 30 to Shobe Road (Project 1)

Status:

  • Submitted 60 percent plans to City of Bryant and ARDOT
  • Proceeding with final plans and quantities
  • Setting up coordination meeting with utilities

Schedule:

  • 60% Plans Submittal:               September 2017
  • Final Plans Submittal:              October 2017
  • Bid Opening Date:                    November 2017
  • Planned Construction Date:     December 2017


Bryant Parkway Shobe Road to Reynolds Road (Project 2)

Status:

  • In September the Saline County Airport Commission voted to select Alternative E as their preferred alternative route.  The Commission is drafting a letter of support.
  • Once the letter of support is receive, Garver will continue coordination with the FAA
  • Coordination has started with Josh Minton regarding the proposed Bryant Middle School. 

Schedule:

  • Feasibility Study Submittal:      October 2017
  • Planned Survey Start Date:      November 2017
  • Planned Design Start Date:      December 2017
  • Planned Construction Date:     January 2019 (from Feasibility Study)

(N) Bryant Parkway: Highway 5 to Hilldale Road

Status:

  • 30 percent Design and Cost Estimate Complete
  • Environmental permitting process has begun 
  • Access Management plan is being revised to include Hwy 5 to Hilldale Rd.

Schedule:

  • 30 percent Plans Submittal:        September 2017
  • 60 percent Plans Submittal:        November 2017
  • Final Plans Submittal:                 January 2017
  • Planned Construction Date:        February 2017


Sidewalks

Sidewalks at Elm Street and Third Street

Status:

  • Metroplan TAP grant for this project is currently in process of being combined with the ARDOT Tap grant which will allow both of these grants to be executed as one project. 

Schedule:

  • 30 percent Plans Submittal:           Three Months- Following Notice to Proceed 
  • 60 percent Plans Submittal:           Five  Months- Following Notice to Proceed
  • Final Plans Submittal:                     Eight Months- Following Notice to Proceed 
  • Planned Construction Start Date:   Nine Months- Following Notice to Proceed

imagejpeg_0

Fire Station Project Summaries

Springhill Fire Station

Status:

  • Land Purchase Complete         September 2017
  • Goes out to Bid                         October 2017

Schedule:

  •  Bid Review Day                        November 9, 2017  
  • City Council Approval                November 2017
  • Construction Begins                  December 2017
  • Construction Complete              October 2018

Hill Farm Fire Station

Status:

  • Land Purchase Complete        September 2017
  • Goes out to Bid                        October 2017

Schedule:

  • Bid Review Day                        November 7, 2017
  • City Council Approval               November 2017
  • Construction Begins                 November 2017
  • Construction Complete             October 2018

           

Parks and Recreation Projects Summaries

*Project designs and timelines are subject to change as projects progress.

Mills Park Restroom Facility

Status:

  • Goes out to Bid                          November 2017

Schedule:

  • Bid Review Day                         December 7, 2017
  • City Council Approval                January 2018
  • Construction Begins                  January 2018
  • Construction Complete              March 2018

Shade Structures Bishop Park

Status:

  • Received Council Approval      August 2017

Schedule:

  • Construction Begins                 October 2017
  • Completion Date                       January 2018

New Grounds Building Bishop Park

Status:

  • Goes out to Bid                          November 2017

Schedule:

  • Bid Review Day                         November 30, 2017
  • City Council Approval                December 2017
  • Construction Begins                  December 2017
  • Construction Complete              April 2018

New Park- North of Interstate

Status:

  • Land Purchase Completed- Approximately 40 acres west of Midland Park
  • Future plans include additional soccer fields along with walking and biking trails

Schedule:

  • To Be Announced


Bishop Center Remodel

Status:

  • Goes out to Bid                            November 2017

Schedule:

  • Bid Review Day                            December 14, 2017
  • City Council Approval                   January 2018
  • Construction Begins                     April 2018
  • Construction Ends                        August 2018

Bishop Parking Lot and Landscaping

Status:

  • Goes out to Bid                         December 2017

Schedule:

  • Bid Review Day                          December 14, 2017
  • City Council Approval                 December 2017
  • Work Begins                               April 2018
  • Work Completed                         May 2018  

Pavilion at Bishop Park

Status:

  • Goes out to Bid                            November 2017

Schedule:

  • Bid Review Day                            November 30, 2017
  • City Council Approval                   December 2017
  • Construction Begins                     December 2017
  • Construction Complete                 January 2018

Mills Parks All Inclusive Playground

Status:

  • Planning Completed

Schedule

  • Playground Closure/Deconstruction    December 2017
  • Dirt Work and New Equipment             April 2018
  • Pour and Play Surface                         March 2018
  • Playground Reopens                            March 2018      

Mills Park Trails Update

  • Info coming soon!      

Stormwater Project  Summaries

coming_soon

 










Sign up today for Notify MeNotify MeStay up to date on ALL City News and Events