×
Show Main Menu
Springhill/Hilltop Drainage Project Project photo

Springhill/Hilltop Drainage Project

DATES: Mar 14, 2022 - Jun 29, 2022

2021- The city receives notification that the city has been awarded $300,000 from the Arkansas Department of Emergency Management State Mitigation Program Grant to be used towards the completion of this project. 

2021-  Design work is completed, this project is submitted for consideration for a grant from the Arkansas Department of Emergency Management State Mitigation Program. 

2020- RFP for design is placed out for public bid.  Bid received and local engineering firm selected. 

2019 -  Due to repeated closures and safety concerns the Hilltop/Springhill Road intersection was identified as a priority stormwater project by city staff. 

Project Updates

PROJECT COMPLETE Project photo
PROJECT COMPLETE

DATE: Dec 07, 2022

Before and After Project photo
Before and After

DATE: Jun 09, 2022

Drainage upgrade seems to have worked on Hilltop and Springhill

Before and After photo 0
Hilltop rd. west of miller rd closing today  Project photo
Hilltop rd. west of miller rd closing today

DATE: Jun 07, 2022

All, Hilltop west from Miller road to Springhill will be close to through traffic until 1:00pm today. This is for the new asphalt work being constructed at the intersection of Hilltop/Springhill road.

Temporary Lane Disruption 6/2/2022  Project photo
Temporary Lane Disruption 6/2/2022

DATE: Jun 01, 2022

Contractor will be laying the final layer of asphalt on Springhill and Hilltop Thursday 6/2/2022. This should be the last road interruption for this project.

Road Closure Thursday 5/12/22 starting at 9 AM - 3 PM Project photo
Road Closure Thursday 5/12/22 starting at 9 AM - 3 PM

DATE: May 11, 2022

Hilltop road at the intersection of Springhill will close once more for the drainage project. Thursday 5/12/22 starting at 9 AM - 3 PM. 

Hilltop Re-opens Wednesday 5/4/2022 at 2:00 pm Project photo
Hilltop Re-opens Wednesday 5/4/2022 at 2:00 pm

DATE: May 04, 2022

5/2/2022 Hilltop Road Closure Rescheduled due to weather--- date pending.  Project photo
5/2/2022 Hilltop Road Closure Rescheduled due to weather--- date pending.

DATE: Apr 28, 2022

The Hilltop road closure will not be tonight as planned due to unforeseen circumstances. As of now the Hilltop road closure is rescheduled for Monday night 5/2/2022 weather permitting.


The 5/2/2022 road closure has been canceled due to weather.  We will reschedule and send out additional notifications. 

Hilltop Road Closure Project photo
Hilltop Road Closure

DATE: Apr 26, 2022

Contractor will be working Thursday night 4/28 to cross Hilltop with this section of our drainage project. The section of Hilltop will close to through traffic from Miller road to Springhill. Road closure will begin at 6:00 PM pending traffic at this time. 7:00 PM will be the latest to start the closure and be reopened at 7:00 AM Friday morning.

Both traffic lanes are open Project photo
Both traffic lanes are open

DATE: Apr 25, 2022

Both lanes on Springhill road are now open. The traffic lights on Springhill road are set to flashing yellow and the traffic light on Hilltop is set to flashing red until Arkansas sign and banner can pull them out.

Plans to open both lanes  Project photo
Plans to open both lanes

DATE: Apr 20, 2022

4/20/20220  The Contractor plans' to have both lanes open by Monday or Tuesday of next week but construction will be ongoing for the next week or so.   

Traffic Pattern Change Project photo
Traffic Pattern Change

DATE: Apr 18, 2022

Starting Tuesday morning 4/19/2022 traffic for Springhill road will have a lane swap. Traffic will now flow in the west lane of Springhill road as the drainage project continues for the east side of Springhill road.

Alternative Route Project photo
Alternative Route

DATE: Apr 11, 2022

Consider using alternative routes beginning 4/12/2022 

Upcoming Traffic Pattern Change   Project photo
Upcoming Traffic Pattern Change

DATE: Apr 05, 2022

On or about 4/12/2022 traffic pattern will change to single lane traffic while new drainage culverts are being installed.  

Traffic Pattern Change Project photo
Traffic Pattern Change

DATE: Mar 29, 2022

3/29/2022 As of today the temporary traffic signals set up on Springhill road for our drainage project at the intersection of Hilltop will now flash red.  

Traffic Pattern Change Project photo
Traffic Pattern Change

DATE: Mar 28, 2022

3/29/2022. The north bound lane of Springhill road at the intersection of Hilltop will be down to one lane from 9: AM - 11:00 Am Tuesday 3/29/2022. 
This lane closure is for the ongoing storm drain project in the area. More updates will follow as more dates are set to install the culverts across Springhill road/Hilltop.
Road Closure at 3:00 PM  Springhill/Hilltop Drainage  Project photo
Road Closure at 3:00 PM Springhill/Hilltop Drainage

DATE: Mar 18, 2022

Redstone will have the northbound lane on Springhill Road, south of Hilltop down to one lane at 3:00 PM today, March 18th.  This closure will be for a concrete truck to pour concrete for the ongoing drainage project. 

Traffic Pattern Change Project photo
Traffic Pattern Change

DATE: Mar 18, 2022

This intersection will experience a change in traffic flow sometime in the upcoming week, depending on weather. We anticipate construction on this intersection to begin on Tuesday, March 22nd but could be delayed if impacted by rain.  Construction will be ongoing for the next two months so please use caution while traveling in this area and schedule extra time to reach your destination.  We appreciate your patience as we complete this Storm Water project and improve public safety in this area.  

Grant Awarded - Springhill/Hilltop Drainage Project Project photo
Grant Awarded - Springhill/Hilltop Drainage Project

DATE: Mar 15, 2022

September 2021 the following press release was sent out to the public:

From the Desk of Mayor Allen Scott

FOR IMMEDIATE RELEASE

City of Bryant Awarded State Mitigation Grant Money for Springhill/Hilltop Road Drainage Improvement Project

During Tuesday night’s city council meeting Mayor Allen Scott announced that the City of Bryant is a recipient of a $300,000.00 grant from the Arkansas Department of Emergency Management’s state mitigation grant program for the Springhill/Hilltop Road Drainage Project.

The project has a projected total of approximately $580,000 will be a complete replacement of the existing drainage system, upgrading to a box culvert system, and significantly reducing the chance of flooding during regular rain events in the future. 

“The Springhill/Hilltop intersection is recognized as a repeated loss by the state, meaning the city can show multiple instances of flooding and the impact it has on the community.  This issue has been an ongoing public safety concern when we have bad weather for our first responders and the residents in the area.  I am glad to see we will be able to move this project forward quickly”, states Mayor Allen Scott.

“The design work is completed,” adds Public Works Director Tim Fournier.  “We anticipate construction to begin in 2021 with an estimated completion date of the first quarter, 2022. For questions regarding this project, you can contact the mayor’s office at 501-943-0302.

Contact Information

Engineering Dept. Ted Taylor

Phone Email

Project Files:

Check Out more City of Bryant Projects

Sign up for updates about this project